Highway Contractor: Three Case Studies; Three Choices
HighwayContractor
by Dan Brown, Contributing Editor
HOT
F
FNF Construction earned mix
quality bonuses averaging
$2.30 per ton.
NF Construction and the Arizona
Department of Transportation
(ADOT) set the bar very high
these days in hot mix asphalt paving on
Interstate highways. Consider, for example,
an 18-mile-long project on Interstate
10 in Cochise County. Not only did FNF
achieve high rates of production on the
$10.3 million project,
but the company also
won bonuses for both
smoothness and mix
quality. And, the project won a Quality in
Construction Award
from the National
Asphalt Pavement
Association and a
Build Arizona Award
from the Associated
General Contractors.
“We moved down
the road pretty good,” says Clint Amator,
FNF project manager. “On some days we
laid around 3,000 tons, and we had a few
days where we actually placed more than
5,000 tons. Over the course of the project,
we averaged right at 3,500 tons of asphalt
per day.”
FNF ran a 24-hour traffic control operation for the project. “We were working
about an 18-hour milling shift to keep
up with our paving operations, so we really had to resource the project 24 hours
a day to keep the traffic control running,”
Achieving the high
production/quality
double on Interstate 10
Amator says. The contractor kept traffic
running in one lane at all times. ADOT
limited the length of the one-lane closure
to 4 miles.
Using one Roadtec RX 900 milling machine, subcontractor Valentine Surfacing of
Vancouver, Wash., milled the pavement at
12.5 feet wide. Depths of milling ranged
up to 5 inches. “When we did the 5-inch
milling we were getting roughly 2 miles
per day,” Amator says. “But when we were
actually milling 3.5 inches, then putting
back 3 inches of dense-graded mix, we
achieved close to 3.5 to 4 miles per day
on that.”
Amator says the major challenge of
the project was the differential milling
required to correct the cross-fall on superelevations where the pavement curved. As
designed, ADOT called for the cross-fall
to be corrected in the paving phase. But
because ADOT and FNF practiced partnering on the project, ADOT accepted FNF’s
proposal to correct the cross-fall in the
milling phase.
“If we saw a problem, we brought it
up right away before it manifested itself
into a real issue,” says Amator. “ADOT
worked very well with us to listen to our
concerns. For any potential problem, we
put it out in the open and proposed a
solution for them prior to having delays.
Our handling of the super-elevations is
an example of that.”
The original plans called for increases in
Better Roads August 2012 9